Salem State University
Project Number: SAL-0832-18
Completion date: August, 2019
Status: Complete
Architect: Miller Dyer Spears
Construction Manager: Walsh Brothers, Inc.
Project Manager: LeftField Project Management
Renovation of existing bathrooms in Peabody Hall and Bowditch Hall Dormitories originally built in 1960s. Renovations include complete gut and fit-out of bathrooms including expanding floor space into existing elevator shaft, new duct work and plumbing risers and distribution systems, new fixtures, new interior wall layout and finishes. Construction to begin mid-May 2019 and be completed by August 2019.